STACK Infrastructure
TORONTO, ON (DECEMBER 2022)
Quasar has partnered with STACK Infrastructure to deliver commissioning services across multiple major builds at their Toronto campus, supporting Canada’s rapidly growing hyperscale and colocation market.
Our work has included:
DH110A: Commissioning of a full power block including 3×3MVA transformers, 3×3MW generators, 3×2.4MW UPS systems, 3×4000A switchboards, and associated downstream distribution and RPPs.
DH110B: Commissioning of the Pearl Backfill project, with a 3MVA transformer, 3MW generator, 2.4MW UPS, and critical distribution upgrades.
Pearl UPS Replacement: Commissioning of a new UPS system in a live environment, with Level 3 and 4 testing executed under strict methods-of-procedure to ensure uninterrupted operations.
Across these projects, Quasar delivered integrated Level 0–5 commissioning using digital CxAlloy documentation and tracking, ensuring quality, transparency, and accountability from pre-functional through integrated systems testing.
Together, these projects reinforce Quasar’s ability to deliver complex, high-density infrastructure under demanding timelines, establishing STACK’s Toronto sites as resilient, scalable, and future-ready data centre assets.
Services Provided: Design-Build, Master Planning, Electrical & Mechanical Engineering, Commissioning